NDRC Work #7-A

Posted By admin On December 27, 2009 @ 2:47 pm In Completed Projects | Comments Disabled

Project Name
:
PUMPING STATION X1 AND ITS RISING CONTRACT NO. DS 161.
Client
:
DUBAI MUNICIPALITY DRAINAGE & IRRIGATION DEPT.
Consultant
:
ACE INTERNATIONAL ASSOCIATE CONSULTING ENGINEERING
Contractor
:
HEDLEY INTERNATIONAL EMIRATES CONT. L.L.C
Sub Contractor
:
EFFICIO TUNNELING L.L.C

MICRO TUNNELING DRIVE DETAILS
Location: Lihbab Road
Location No.: 08
Total Length: 2 Lines X 216 Meters = 432 Meters
Drive Started Date: 12/11/2009
Drive Completed Date: